Getting Your Building Permit in Kenya

A step-by-step guide to the NCA approval and county permit process

Overview

In Kenya, all buildings above a certain threshold require approval from:

  • National Construction Authority (NCA) - mandatory NCA project registration for contracts above KES 5M or >50m².
  • County government - building plan approval from the relevant county, such as City of Nairobi or Kiambu County.
  • NEMA - Environmental Impact Assessment for larger or environmentally sensitive projects.

This guide covers the typical process for a 3-5 bedroom residential house.

Step-by-step process

  1. 1

    Engage a registered architect

    Use a BOR-registered architect to prepare the drawing set. ArchTx connects you with verified architects.

    2-4 weeks for drawing set.

  2. 2

    Submit architectural drawings to the county planning office

    Typical documents include 4 copies of approved drawings, site plan, title deed or allotment letter, and owner ID.

    4-12 weeks depending on county.

  3. 3

    Register the project with NCA

    Register online at nca.go.ke if contract value is above KES 5M. Upload the contract, architect certificate, and drawings.

    Fee is a sliding scale based on project value.

  4. 4

    Use an NCA-registered contractor

    NCA-registered contractors are required. ArchTx's contractor network is verified for NCA registration.

    Confirm before signing the construction contract.

  5. 5

    Check whether NEMA EIA applies

    A standard residential house typically does not require EIA; larger sites, sensitive sites, and wetland-adjacent projects may.

    Confirm early if the site is above 0.5 ha or environmentally sensitive.

  6. 6

    File commencement notice

    Notify the county and NCA before breaking ground.

    Before site mobilisation.

  7. 7

    Complete stage inspections

    Plan for inspections at foundation, slab, wall plate, roof, and occupation-certificate stages.

    Throughout construction.

  8. 8

    Obtain occupation certificate

    Get the county occupation certificate on completion before occupying the building.

    After final inspection.

County contacts

Verify contact details directly with the county - offices change frequently.

CountyPlanning OfficePhoneOnline portal
NairobiCity Hall Annex, Urban Planning+254 20 222 4281Nairobi e-Development / County portal
KiambuKiambu County Headquarters, Physical Planning+254 66 202 0150Kiambu County e-services
MombasaMombasa County Physical Planning+254 41 222 2121Mombasa County portal
NakuruNakuru County Physical Planning+254 51 221 4142Nakuru County portal
KisumuKisumu County Physical Planning+254 57 202 3810Kisumu County portal
Uasin GishuEldoret Physical Planning Office+254 53 201 6000Uasin Gishu County portal
MachakosMachakos County Physical Planning+254 44 202 0116Machakos County portal
KajiadoKajiado County Physical Planning+254 45 212 3080Kajiado County portal

Common mistakes and how ArchTx helps

Using an unregistered architect

ArchTx only lists BOR-verified architects.

Unlicensed contractor

ArchTx verifies NCA registration.

Skipping NCA registration

ArchTx reminds you at project creation.

No stage inspections

ArchTx's supervisor feature logs inspections with photo evidence.

Section 6: Green Building

Plan off-grid utilities while the architectural and roof layouts are still easy to adjust.

Resources

This guide is for informational purposes. Consult a registered architect and the relevant authorities for your specific project.